Victory Sewer Offsite Sewer

The Base Phase 1, LLC

General Contractor:  Willmeng Construction


Project Cost: $2.366 million


Scope: Offsite sewer line, manhole installations, and asphalt improvements


Sewer Line Installation:

Installed 1,766 feet of 15” SDR-35 PVC

Installed 2,858 feet of 12” SDR-35 PVC

Installed 12 EA 60” manholes with 30” ring and cover, coated with insecticide paint and sewer shield


Asphalt Replacement:

Replaced 4,500 square yards of asphalt


Additional Services:

Confined space entry for pipe cleaning and preparation

Traffic control and public outreach

Multi-jurisdictional coordination